Regal Residence Luxury is progressing on schedule, with key construction milestones being completed before the Lunar New Year holiday 2025. VictoryCons continues to maximize resources to ensure the project’s quality and timeline align with the established plan.
Detailed Construction Progress – January 2025:
13/01/2025: Bored pile construction P6A.1; P2.5, P2.8; P2.14, P8.8; P6.27
16/01/2025: Bored pile construction P2.17; P6A.7, P8.6; P2.3
18/01/2025: Bored pile construction P2.13; PCT1, P6.22; P2.7; PCT2, P1.1; P6.10
21/01/2025: Bored pile drilling P1.4; P8.11, P6.26; P2.4, P2.15; PCT3
24/01: Site cleaning and land grading in preparation for Lunar New Year
VictoryCons is strictly following the project timeline and ensuring that all key construction phases are completed on time and to the highest quality standards. The bored pile works have been executed according to technical specifications, ensuring precision and structural safety.
VictoryCons will accelerate progress immediately after the Lunar New Year, ensuring that the project remains on track for timely handover, meeting technical and quality standards for Regal Residence Luxury. We will continue to provide regular updates in our upcoming construction reports.
New strategy, new team – VictoryCons lays the foundation for success in 2025
The Most Comprehensive Legal Framework for High-Rise Real Estate Projects
Construction Progress of Cara River Park – January 2025
The Stages That Maximize Value and Profit for a Project