Construction progress of Regal Residence Luxury (Quang Binh) – November 2024
The Regal Residence Luxury project, located in a prime location along Vo Nguyen Giap Street, Bao Ninh Peninsula, Dong Hoi City, Quang Binh Province, is progressing rapidly with strong commitment from the VictoryCons construction team.
August 15, 2024: Commencement of diaphragm wall construction.
October 15, 2024: The VictoryCons construction team successfully completed the installation of 68/68 diaphragm wall panels, achieving 100 percent of the planned target.
November 2024: The foundation piling phase is currently 97/142 piles completed, reaching approximately 68 percent progress on this critical structural component.
As the general contractor of the project, VictoryCons maintains rigorous quality control, strict adherence to safety standards, and precise execution of the construction timeline. Every phase is carried out as scheduled, with strict supervision to meet the highest technical standards.
New strategy, new team – VictoryCons lays the foundation for success in 2025
The Most Comprehensive Legal Framework for High-Rise Real Estate Projects
Construction Progress of Cara River Park – January 2025
The Stages That Maximize Value and Profit for a Project