In January 2025, VictoryCons has maintained stable construction progress for the 204 adjacent townhouses at Gem Sky World. The construction work has been carried out synchronously and efficiently, from land grading to finishing stages such as wall plastering, waterproofing, painting, and door installation.

With a total area of 92.2 hectares and a diverse range of real estate products including townhouses, villas, shophouses, and land lots, this project is expected to become a high-end urban area, attracting strong interest from investors, especially as the Long Thành Airport area continues to develop rapidly.

Construction Progress – January 2025

  • 1/1/2025 – 24/1/2025: Land grading, base rock placement inside houses and front yards.

  • 1/1/2025 – 24/1/2025:Wall plastering and beam reinforcement.

  • 1/1/2025 – 24/1/2025:Waterproofing work.

  • 1/1/2025 – 24/1/2025:Interior and exterior painting.

  • 1/1/2025 – 24/1/2025:Installation of doors.

  • 1/1/2025 – 24/1/2025:Balcony railing installation.

  • 1/1/2025 – 24/1/2025:Steel frame installation and roof tiling.

  • 1/1/2025 – 24/1/2025:Tile flooring and wall tiling.

With a team of skilled engineers and workers, VictoryCons is committed to closely monitoring the progress and quality of construction, ensuring that the project is completed on schedule and delivers long-term value to the development.

 

Tin tức khác

New strategy, new team – VictoryCons lays the foundation for success in 2025

On March 13, 2025, at the headquarters of VictoryCons Joint Stock Company, a significant event took place, including the Appointment...

The Most Comprehensive Legal Framework for High-Rise Real Estate Projects

 The legal framework for high-rise real estate projects is fully regulated under the latest provisions of the Investment Law...

Construction Progress of Cara River Park – January 2025

The Cara River Park project continues to achieve impressive construction progress in January 2025. The construction activities have been carried...

VictoryCons celebrates International Women’s Day on March 8 and birthdays of employees born in January, February, and March

On March 8, VictoryCons hosted a warm and joyful event to honor the incredible women of the company while also...

The Stages That Maximize Value and Profit for a Project

 During project development, core factors such as legal compliance, planning, product positioning, and business strategy play a crucial role...
0
Would love your thoughts, please comment.x
()
x