Hello dear customers and partners of VictoryCons!
In June 2025, VictoryCons continues to implement parallel construction of two main items at the Gem Sky World project (Dong Nai): the area of ​​35 Shophouses and 204 adjacent houses. The construction site is organized seriously, following technical procedures and ensuring the highest level of labor safety.

AREA 35 SHOPHOUSES

  • VictoryCons labor safety work
    continues to maintain and strengthen safety measures at construction sites, including: construction area barriers, safety signs, full personal protective equipment and organizing morning meetings at construction teams.

  • Structural construction
    In June, structural items were deployed simultaneously along the vertical direction of the project, including:

Construction of stairs for floors 1-2

Construction of columns for floors 1-2

Construction of columns for floors 2-3

Construction of 3rd floor columns – roof

Construction of beams

Construction of 2nd floor beams

Construction of 3rd floor beams

The above works are continuously deployed, ensuring the correct construction methods and progress committed to the Investor.

AREA OF 204 TOWNHOUSES

  • VictoryCons defect repair work
    is focusing on handling small defects remaining after construction, including: cracks in walls, paint patches, tile joints, finishing accessories… Defects are checked and evaluated according to the quality checklist before accepting each apartment.

  • Handover work
    Along with the technical completion, the handover work to customers is being implemented as planned. The technical and customer care teams coordinate closely in each stage, from general cleaning, user instructions to receiving feedback after handover.

VictoryCons is committed to maintaining construction quality, ensuring progress and absolute safety at the Gem Sky World project. We are proud to accompany the Investor in creating a modern, synchronous urban area ready to welcome residents.
We sincerely thank our customers and partners for always trusting and accompanying VictoryCons!

Tin tức khác

VictoryCons accompanies Sports Festival 2025 – Phase 2

After the success of phase 1, Sports Festival 2025 officially returns with phase 2 from October 12 to November 30,...

VICTORYCONS WISHES VIETNAMESE WOMEN’S DAY OCTOBER 20

October 20th – Vietnamese Women’s Day is a special occasion to send gratitude and congratulations to Vietnamese women in general,...

VICTORYCONS ORGANIZES PERIODIC HEALTH CHECK-UPS FOR EMPLOYEES

With the motto “People are the most valuable asset”, VictoryCons always considers taking care of the health and life of...

TEAM BUILDING VICTORYCONS 2025 – OVERCOMING THE WAVES TOGETHER

Recently, VictoryCons organized the Team Building 2025 program with the theme “Overcoming the waves together” at Yen Village Tourist Area...

VictoryCons was honored in the Top 10 Best Design – Construction Contractors in Vietnam 2025 – Breakthrough with a series of trillion-dollar contracts

Within the framework of the Vietnam Excellence Brand 2025 Announcement Ceremony, organized by the Institute for Enterprise Quality Assessment and...