The 2FY Project in District 1, executed by VictoryCons, is progressing according to plan, ensuring on-schedule completion and strict compliance with technical standards. In December 2024, key construction tasks have been completed as follows:
December 1 – December 7, 2024: Fabrication and installation of reinforcement and formwork, concrete pouring for the ramp and septic tank walls in the basement.
December 8 – December 11, 2024: Fabrication and installation of reinforcement and formwork, concrete pouring for the septic tank cover and starter slab for the first-floor stairs.
December 12 – December 15, 2024: Concrete curing and site cleaning.
December 16 – December 22, 2024: Clearing construction materials, relocating machinery, and removing support props from the site.
December 23 – December 24, 2024: IBS/T unit conducting crack inspection survey.
With its expertise and professional construction capacity, VictoryCons is committed to delivering high-quality work, adhering to the project timeline, and ensuring compliance with technical safety standards. We will continue to provide updates in the upcoming phases so that stakeholders can closely monitor the project’s progress.
New strategy, new team – VictoryCons lays the foundation for success in 2025
The Most Comprehensive Legal Framework for High-Rise Real Estate Projects
Construction Progress of Cara River Park – January 2025
The Stages That Maximize Value and Profit for a Project