The 2FY Project in District 1, a mixed-use development combining private housing and office space, is currently progressing according to the planned schedule.

To ensure both progress and quality, each construction phase has been carried out meticulously, adhering to established technical standards. Below is the detailed construction progress update for November 2024.

November 1 – November 2, 2024: Concrete pouring for basement B1 slab beams.

November 2 – November 4, 2024: Concrete curing, column reinforcement, and formwork fabrication for basement 1 columns.

November 5 – November 7, 2024: Removal of the first layer of shoring and kingpost extraction.

November 8 – November 9, 2024: Column and wall reinforcement, formwork, and concrete pouring from basement 1 to floor 1 (Zone 1).

November 9 – November 13, 2024: Steel reinforcement installation, formwork assembly, and concrete pouring for floor 1 beams and slab (Zone 1).

November 14 – November 17, 2024: Concrete curing, column reinforcement, and formwork fabrication for basement 1 columns (Zone 2).

November 18 – November 19, 2024: Removal of the first layer of shoring, platform disassembly, and kingpost extraction.

November 20 – November 22, 2024: Column and wall reinforcement, formwork, and concrete pouring from basement 1 to floor 1 (Zone 2).

November 23 – November 28, 2024: Steel reinforcement installation, formwork assembly, and concrete pouring for floor 1 beams and slab (Zone 2).

November 29 – November 30, 2024: Concrete curing.

The 2FY Project in District 1 is progressing on schedule, with structural components being carefully constructed and strictly following technical procedures. The VictoryCons construction team has successfully fulfilled its tasks, laying a solid foundation for the upcoming phases. The project not only meets the expected timeline but also ensures exceptional quality, exceeding the investor’s expectations.

Tin tức khác

New strategy, new team – VictoryCons lays the foundation for success in 2025

On March 13, 2025, at the headquarters of VictoryCons Joint Stock Company, a significant event took place, including the Appointment...

The Most Comprehensive Legal Framework for High-Rise Real Estate Projects

 The legal framework for high-rise real estate projects is fully regulated under the latest provisions of the Investment Law...

Construction Progress of Cara River Park – January 2025

The Cara River Park project continues to achieve impressive construction progress in January 2025. The construction activities have been carried...

VictoryCons celebrates International Women’s Day on March 8 and birthdays of employees born in January, February, and March

On March 8, VictoryCons hosted a warm and joyful event to honor the incredible women of the company while also...

The Stages That Maximize Value and Profit for a Project

 During project development, core factors such as legal compliance, planning, product positioning, and business strategy play a crucial role...
0
Would love your thoughts, please comment.x
()
x