5/5 - (2 votes)

Cara River Park is considered one of the largest condominium projects in Can Tho at present. Located in Cai Rang District, the city’s new development hub, the project boasts a total construction area of 36,000m², featuring nearly 400 modern apartments, a high-rise complex, a bustling commercial center, office spaces, and adjacent residential areas.

The Cara River Park project is progressing according to schedule, with significant advancements made in December 2024. Below are the key activities carried out from December 18 to December 24, 2024:

December 18, 2024 – December 20, 2024: Conducting structural surveys

December 18, 2024 – December 20, 2024: Executing construction level marking

December 19, 2024 – December 21, 2024: Inspecting incoming materials

December 20, 2024: Implementing temporary electrical and water systems

December 21, 2024 – December 23, 2024: Conducting material testing

December 23, 2024 – December 24, 2024: Receiving material deliveries

With stable construction progress and strict oversight from the project management team, Cara River Park is steadily moving toward its goal of completing a high-quality development.

VictoryCons will continue to provide detailed updates in upcoming articles to ensure that customers and partners stay informed about the project’s latest progress.

Tin tức khác

New strategy, new team – VictoryCons lays the foundation for success in 2025

On March 13, 2025, at the headquarters of VictoryCons Joint Stock Company, a significant event took place, including the Appointment...

The Most Comprehensive Legal Framework for High-Rise Real Estate Projects

 The legal framework for high-rise real estate projects is fully regulated under the latest provisions of the Investment Law...

Construction Progress of Cara River Park – January 2025

The Cara River Park project continues to achieve impressive construction progress in January 2025. The construction activities have been carried...

VictoryCons celebrates International Women’s Day on March 8 and birthdays of employees born in January, February, and March

On March 8, VictoryCons hosted a warm and joyful event to honor the incredible women of the company while also...

The Stages That Maximize Value and Profit for a Project

 During project development, core factors such as legal compliance, planning, product positioning, and business strategy play a crucial role...
0
Would love your thoughts, please comment.x
()
x