The Cara River Park project continues to achieve impressive construction progress in January 2025. The construction activities have been carried out continuously and efficiently, with key tasks being executed to ensure both quality and overall project timelines.

Construction Progress in January 2025:

  • 2/1/2025 – 10/1/2025:

    • Surveying reference lines: Implementation of reference marking for finishing construction activities.

  • 4/1/2025 – 12/1/2025:

    • Structural survey: Checking for defects, verifying slab elevation before proceeding with finishing work.

  • 2/1/2025 – 31/1/2025:

    • Material testing: Conducting quality control tests on incoming construction materials before execution, ensuring compliance with current construction standards and regulations.

  • 2/1/2025 – 31/1/2025:

    • Wall construction:
      • Tower A: 5th floor (80% completed), 6th floor (61% completed).
      • Tower B: 5th floor (80% completed), 6th floor (35% completed).
      • Overall progress: 50% completion as per schedule.

  • 3/1/2025 – 15/1/2025:

    • Material testing: Evaluating the quality of construction materials to ensure they meet durability and safety requirements.

  • 2/1/2025 – 10/1/2025:

    • Temporary electrical and water system installation: Installing the temporary electrical and water systems to support construction work in the initial stages.

  • 2/1/2025 – 31/1/2025:

    • Material procurement: Ensuring a continuous supply of materials for various construction phases, preventing disruptions in execution.

Overall Assessment:

In January 2025, the construction works at Cara River Park continued to be executed systematically and effectively. Key activities such as reference line marking, structural surveys, wall construction, and material quality testing have been completed on schedule. The project remains on track, with strict supervision in place to maintain quality and progress.

VictoryCons is committed to maintaining work efficiency and construction timelines, ensuring the timely completion of the project while fully meeting the expectations and requirements of the investor.

Tin tức khác

New strategy, new team – VictoryCons lays the foundation for success in 2025

On March 13, 2025, at the headquarters of VictoryCons Joint Stock Company, a significant event took place, including the Appointment...

The Most Comprehensive Legal Framework for High-Rise Real Estate Projects

 The legal framework for high-rise real estate projects is fully regulated under the latest provisions of the Investment Law...

VictoryCons celebrates International Women’s Day on March 8 and birthdays of employees born in January, February, and March

On March 8, VictoryCons hosted a warm and joyful event to honor the incredible women of the company while also...

The Stages That Maximize Value and Profit for a Project

 During project development, core factors such as legal compliance, planning, product positioning, and business strategy play a crucial role...

Topping-Out Ceremony of Cara River Park – VictoryCons and Cara Group Creating a New Landmark

On March 5, 2025, the Topping-Out Ceremony of Cara River Park officially took place, marking a significant milestone as the...
0
Would love your thoughts, please comment.x
()
x