Cara River Park is considered one of the largest condominium projects in Can Tho at present. Located in Cai Rang District, the city’s new development hub, the project boasts a total construction area of 36,000m², featuring nearly 400 modern apartments, a high-rise complex, a bustling commercial center, office spaces, and adjacent residential areas.
The Cara River Park project is progressing according to schedule, with significant advancements made in December 2024. Below are the key activities carried out from December 18 to December 24, 2024:
December 18, 2024 – December 20, 2024: Conducting structural surveys
December 18, 2024 – December 20, 2024: Executing construction level marking
December 19, 2024 – December 21, 2024: Inspecting incoming materials
December 20, 2024: Implementing temporary electrical and water systems
December 21, 2024 – December 23, 2024: Conducting material testing
December 23, 2024 – December 24, 2024: Receiving material deliveries
With stable construction progress and strict oversight from the project management team, Cara River Park is steadily moving toward its goal of completing a high-quality development.
VictoryCons will continue to provide detailed updates in upcoming articles to ensure that customers and partners stay informed about the project’s latest progress.
New strategy, new team – VictoryCons lays the foundation for success in 2025
The Most Comprehensive Legal Framework for High-Rise Real Estate Projects
Construction Progress of Cara River Park – January 2025
The Stages That Maximize Value and Profit for a Project